The two most important characteristics of a scheduling test are

  • Sufficiency - If a positive outcome guarantees that all deadlines are always met
  • Necessary - If failure of the test will lead to a deadline miss at some point during the execution of the system

Utilization-Based Schedulability Test for FPS